No Coal Coalition Weighs in on White Stallion Court Decision

Allison Sliva is board chair of the No Coal Coalition/Matagorda County.

When I heard the news that EDF’s Motion to Remand was recently granted by Travis County Court Judge Lora Livingston, I was pleased on several fronts.

First, the decision halts, even if temporarily, a process of approving building facility plans that has tried to circumvent air quality laws designed to protect public health. Building this coal plant would bring with it serious air quality impacts for people in and around Matagorda County, not to mention the greater Houston area. Projected emissions from the plant will include 10 million tons of carbon dioxide, nearly 5,000 tons of sulfur dioxide, more than 4,000 tons of nitrogen oxide, nearly 1,800 tons of particulate matter and nearly 100 pounds of mercury.

This pause in the process should make everyone involved – especially the Texas Commission on Environmental Quality – think twice about the air impacts to present and future generations.

Second, the decision exposes a White Stallion action that might otherwise have gone unnoticed. TCEQ granted White Stallion an air permit after reviewing air dispersion modeling and testimony based on a site plan that White Stallion changed six days after the permit was issued. As EDF’s Jim Marston said, White Stallion “should be upfront with regulators about their intentions.”

Third, the decision renews public confidence in our legal system. As Judge Livingston wrote in her decision letter, “Without remand, meaningful public participation in the permit approval process would be effectively eliminated.”

Myself and members of the No Coal Coalition of Matagorda County thank you EDF for your due diligence in helping to set the record straight.  Our call to action now is to help gather the evidence needed to prove that the air pollution coming from White Stallion would violate the law as well as harm human health.

WHITE STALLION TIMELINE

Here is a timeline of the community efforts that Matagorda County residents and others have undertaken over the years to prevent a poorly planned, poorly placed and poorly designed coal-fired power plant from coming online. – Elena Craft

September 2008 – White Stallion files for an air quality permit from the Texas Commission on Environmental Quality. It proposes a 1,320 megawatt coal and petroleum coke-fired power plant to be located along the Colorado River eight miles south of Bay City in Matagorda County, in an ecologically sensitive area known as the Columbia Bottomlands. The proposed location is also 20 miles southwest of the Houston-Galveston-Brazoria region.

November 13, 2009 – In a letter from the Environmental Protection Agency to the U.S. Army Corps of Engineers, Wetlands Section Chief Sharon Fancy Parrish recommended that an Environmental Impact Statement be conducted “for the proposed project to better access the substantial change to the human environment.” Read More »